Technical specifications
| Finish | Egg-shell (black) |
|---|---|
| Type | Water-based acrylic scenic primer and sealer |
| Binder | Acrylic polymer |
| Coverage | Approx. 28 m² per 3.8 L per coat (300 sq ft per US gallon), depending on substrate and method |
| Film thickness | 3 mil dry film (approx. 76 micron) |
| Dry time | Touch dry 30–45 min; recoat in 1–2 hours at 24°C |
| Clean-up | Soap and water |
| Sizes | 3.8 L (1 gallon) and 19 L (5 gallon) |
| Adheres to | Wood (timber, MDF, plywood), metals and aluminium, PVC and plastics, foam, foamcore and muslin |
| Apply with | Brush, roller or spray gun |
Figures per Rosco published data. Coverage varies with surface, porosity and application.
Slip resistance test results
Rosco Tough Prime Black has been independently tested in Australia by a NATA-accredited laboratory in accordance with AS 4586:2013 – Slip resistance classification of new pedestrian surface materials. Each specimen was two coats of Tough Prime Black.
| 19 mm Structural F11 plywood | D1 dry floor friction · P2 wet pendulum (SRV 33) |
|---|---|
| 5 mm Masonite hardboard | D1 dry floor friction · P2 wet pendulum (SRV 33) |
| Test standard | AS 4586:2013 – Appendix B (dry floor friction) and Appendix A (wet pendulum, Slider 96) |
| Laboratory | SlipLab – NATA-accredited testing laboratory (reports 101867 and 101868) |
Results apply to the tested system. Performance on your floor depends on the substrate, preparation, application and maintenance – test on a sample first.
How it goes down
Fast dry times mean more than one coat in a single day, which is why a floor can be resurfaced in a break between shows.
Always test on a sample first — before you go any further
Every project is different: the surface, the substrate, the prep, the traffic, the conditions. No approach applies across the board. Paint a test area of your actual floor, confirm you are happy with the coverage, colour and durability, and document what you did — product, coats, dilution, date. Only then do the whole floor.
Prepare
Clean, dry and sound. Remove loose or flaking paint, vacuum off dust, and lightly abrade glossy or previously coated areas so it can grip.
Seal porous areas
It is the primer, so no separate undercoat is needed. On very absorbent bare MDF, chipboard or raw ply, a thinned first coat evens out the porosity. Concrete needs proper prep first.
First coat
Lay on a thin, even coat by brush, roller or spray. Thin coats level better and dry harder than one heavy coat.
Recoat the same day
Touch dry in 30 to 45 minutes, recoat in 1 to 2 hours. Two coats suits most floors and both can go on in a day. If your floor is porous, a third coat may be needed — always test your own floor first, as every one varies.
Let it cure
Let the finish dry and cure before wagons, equipment and traffic return to the floor. Allow extra time where you can.
Touch up as needed
Later on, scuff the worn area, clean it and recoat. No strip-back, no full repaint unless you want one.
Coverage calculator
Work out how much paint this job needs
Enter your wall, floor or cyc dimensions and get the quantity in gallons and tins, using Rosco's published coverage figures. It covers 18 Rosco products and handles the cove geometry on a curved cyc.
Open the paint coverage calculatorQuestions about your floor?
We are the exclusive Rosco distributor for Australia and New Zealand. Send us a message or give us a call and we will help you work out whether Tough Prime is right for your stage, studio or floor.